-
-
-
-
- Morton
Schoolhouse Restoration News
-
-
-
-
- Exterior
Brickwork
-
- Only
a few days after the bell tower had been installed and
- the
trucks and crane had left, another trailor arrived in the
- school
house parking lot. It was the first of several that are
- being
employed by the crew that will restore the exterior of
- the
building.
-
-
-
- Morton
School - April 2, 2002
-
- There
are multiple steps in the
process required to
- restore the brick
exterior. This will be a summary
- of those used at
the Morton Schoolhouse.
-
-
-
- What
a grind!
-
- Loose
and deteriorated mortar is removed by grinding the
- joints.
All the mortar joints are ground to a depth of about
- 1/2
to 3/4 inch.
-
-
-
- The
front enclosure is removed
-
-
- In
order to facilitate the grinding on the front of
- the
schoolhouse, the enclosure was removed the
- day
after the work had begun.
-
- The
weather has been a mixture of snow, rain,
- and
bits of sunshine for the benefit of the work crews.
-
-
-
- Same
old grind
-
- The grinding of the mortar
joints took the crew about 4 to 5 days
- of
dusty, grimy, work. The rain that occurred was welcomed, since
- it
helped to reduce the amount of dust in the air and helped to
- remove
some of the dust that settled on all the surrounding
- surfaces.
After an area was finished, pressurized water was
- used
to further remove the dust and grime.
-
-
- Face
lift
-
- Once
the surface has been washed, the task of removing
- damaged
bricks begins. Over the years some of the bricks
- have
deteriorated, or have been damaged. If the damage
- is
extensive the brick is removed. In the picture above,
- the
school front has been washed and several bricks in
- the
outer course have been removed.
-
-
-
-
- Bricks on the West
side as well as the remainder of
- the schoolhouse
have been removed.
-
-
-
- The brick used
in the construction of Morton School, as well
- as many of the
early schools, were a soft brick fired at a relatively
- low temperature.
The bricks that are currently manufactured are
- much harder and
of a different size. In order to properly restore the
- building, the bricks
that replace those that have been removed should be
- as similar in appearance,
age, and all other characteristics as possible.
-
- Bricks that the
work crews had reclaimed from other area projects,
- proved to be unsuitable
for Morton School for a variety of reasons.
- When faced with
this dilemma, friends in the community again
- came forward to
help.
-
- Faulkner school, another area one-room school
that was constructed
- at nearly the same
time (1889) as Morton, is currently in bad repair
- and many bricks
are becoming detached from the inner brick courses.
- Current descendants
of the Daniel S. Faulkner family who owned the
- land where their
school was built, agreed to allow the use of some of
- the brick from
their schoolhouse in the restoration of Morton School.
-
- Lawrence Faulkner,
a grandson of Daniel, and his sister, Mrs Doris
- Faulkner /Stotts,
and her daughter Mary Ann Stotts have been closely
- following the Morton
project. When they heard of "brick problem",
- they all agreed
to help and volunteered to participate in removing
- the Faulkner school
bricks. The Faulkner bricks were taken to
- Morton School so
the crew could begin installing them the
- following day.
-
- Now the schoolhouse
with some bricks removed and freshly ground
- mortar joints,
was washed with a mild cleaning solution that removed
- most of the surface
grime, stains, paint wash, and bird droppings that
- had accumulated
over the years.
-
- The Faulkner bricks
were then put in place with a mortar that cures not
- nearly as hard
as the standard mortar commonly used today. Since the
- bricks are a softer
variety, the mortar must be also, so that the relative
- hardnesses are
compatible. Otherwise, today's commonly used mortar after
- a period of time,
would destroy the surface of these brick. Mortar was then
- applied overall
to replace all that was removed in the grinding process.
-
-
-
- Morton
School West Side - April 9, 2002
-
- Newly
cleaned, with some Faulkner School bricks and fresh mortar!
- Doesn't
it look great??
-
-
-
-
- In
another week or so, all the scaffolding and equipment that was
used by
- the
crew from Oak - Stone Renovators, Inc. was gone gone and they
have
- left
us with a beautifully restored building exterior.
-
-
-
- Morton
School House - May 2002
-
-
-
- The
next step is the replastering of the interior . . . .
If
you have additional information that you would like to add to
this page, we
- would
be happy to hear from you. Please email us!!
Copyright
© 2000 - 2018